Investment opportunity.
About
In the Nord-Est of Italy, AGA 4.0 srl company has a project to install the following plants: production well 4.500m deep, ORC plant, H&C exploitation, Green Hydrogen plant, reinjection well.
We will produce the following energies: 28.000 MWh el/y, more than 24.000 MWht/y and Green Hydrogen. The users are: national electrical grid, private turistic harbor and buildings for H&C in 1.500m radius.
The AGA 4.0 project obtained the "Research Geothermal Permit" from regional authorities in 2024 (Regione FRIULI VENEZIA GIULIA).
Financial parameters: total CAPEX c.a 25.000.000 €, Gross Pay-back = 8,6 y, IRR or TIR on equity = 18%, DSCR = 2.
Applies to
- Financing, Business Models
- Socio-economic aspects of geothermal energy